Case Study · Fire Stopping · February 2024

A school kept safe
around the school day.

A secondary school is the definition of a building that cannot stop. As principal contractor for Haringey Council, Gemini AMPM sealed twenty one fire stopping locations through Highgate Wood School and restored its fire door protection, landing the heaviest phase in the summer holidays and closing out the scope with a FIRAS Certificate of Conformity.

The brief

Nineteen breaches,
one live school.

The main scope was penetration sealing: nineteen documented locations from the ground floor stair corridor up through the first, second and third floor ceilings, where services had been cut through fire lines and never properly reinstated. The systems were Nullifire throughout: ablative coated batt and solution, graphite high pressure mastic, intumescent mastic and pipe wraps to sixty minute ratings, with fire rated boarding where openings needed rebuilding. Fire door protection was restored alongside: FD30 components, intumescent strips and rated hardware to tested details.

The programme was built around the pupils. The main phase mobilised in the last week of August, up to eight operatives working through the summer holidays behind barriers and signage, battery tools to keep corridors free of trailing leads, and a full protocol on standby in case works uncovered anything unexpected in a 1950s building fabric.

What we delivered

The scope,
in full.

Penetration sealing

Twenty one locations sealed through four floors with Nullifire batt, ablative solution, graphite HP mastic and intumescent pipe wraps to sixty minute ratings.

Fire door works

FD30 door components restored to tested details: Pyroflex intumescent strips, rated hinges and glazed doorset components.

Term aware programme

Main phase through the summer holidays as principal contractor, up to eight operatives, with public protection measures for a school environment.

Photographic QC

Before, during and after photography at every location, compiled into two report volumes for the council’s compliance file.

The evidence

Photographed before,
during and after.

Every location carries a photographic record from first exposure to finished seal: two report volumes covering the nineteen main locations and a follow up visit in February 2024 that closed out two further locations found in service areas. That final visit completed the certificated scope.

The FIRAS Certificate of Conformity was issued within the week, covering both penetration sealing and timber fire doors under a FIRAS registered supervisor. For a council estate team, that certificate plus the photo record is the file that answers the auditor’s question before it is asked: not that work was done, but that the right systems went into the right holes and can be proven.

Compliance

Delivered
to standard.

  • FIRAS certificated: Certificate of Conformity HL2632 covering penetration sealing and timber doors, under a FIRAS registered supervisor.
  • Tested systems: Nullifire fire stopping and compartmentation systems installed to their assessed performance.
  • CDM 2015: delivered as principal contractor for Haringey Council with school specific RAMS and public protection.
Your project

Planning something
similar?

PQQ-ready evidence and client references behind this project are available on request. A named engineer, not a call centre, comes back within 24 hours.